NewsArena
Newsarena.ng is an online news media established to disseminate up-to-date and unbiased reportage of issues of public concern, with high level of professionalism, based on truth.

Minister Issues Seven-Day Ultimatum To Julius Berger

The Minister of Works, David Umahi, has issued a seven-day ultimatum to Julius Berger to accept the Federal Government’s offer of N740.79bn for the completion of the 82km section II of the Abuja-Kaduna-Zaria-Kano road.

The ultimatum was issued during a courtesy visit to the Minister by the new Managing Director of Julius Berger Plc, Dr Pier Lubasch, accompanied by the outgoing Managing Director, Dr Lars Richter, at the Ministry Headquarters in Abuja.

A statement later signed by the Special Adviser (Media) to the Minister of Works, Orji Uchenna, on Wednesday, said the company risks termination of the contract if it does not accept the offer.

“The Honourable Minister of Works, His Excellency, Sen. Engr. Nweze David Umahi, CON has for the umpteenth time called on Julius Berger Plc. to show corporate patriotism by accepting the Federal Government’s approved reviewed total contract sum of ₦740, 797,204,713.25 (Seven Hundred and Forty Billion, Seven Hundred and Ninety-Seven Million, Two Hundred and Four Thousand, Seven Hundred and Thirteen Naira, Twenty-Five Kobo for the completion of the rehabilitation of the 82 km section II of the Abuja-Kaduna-Zaria-Kano road, contract No.6350.”

He lamented that the delay in mobilising to the site despite the approved funds by the Federal Executive Council is causing untold hardship to the road users and that the Federal Government is at the receiving end of the situation.

Also Read:  Oyo Speaker Congratulates New Deputy Chief of Staff To Gov. Makinde

“So if Berger is not doing it, then let’s have other people to do the job and within the time that we can control price. We’ve had more than 20 letters from Berger on this. It is a ping pong game from Julius Berger. The prices rose from ₦710 billion to ₦740 billion because of these delays. And if we continue the delays, it is the problem of the Ministry of Works.”

Also Read:  2024 LG Poll: OYSIEC Announces Date To Publish Names Of Successful Candidates

The minister expressed dismay that Julius Berger Plc, which has had years of patronage by the Federal Government and sub-national governments, is not realistic in the contract pricing, especially at this time of Nigeria’s economic challenges.

He therefore urged the contractor to within seven days accept or reject the approved reviewed contract sum for the completion of the rehabilitation of section II of the Abuja-Kaduna-Zaria-Kano road, or face contract determination as the Federal Government can not be held to ransom by the desire for unrealistic pricing and augmentation by contractors.

He said, “This offer is not subject to any condition. It’s not subject to any condition that is being dished out here. It’s taken as given after more than 14 months. I’m sorry, I have to sound this way because there must be an end to negotiation. If anybody says there shouldn’t be an end to negotiation, then that person is not a business person. If you have negotiated for 14 months without any result, you should terminate the negotiation.”

Also Read:  Court Remands Pastor In Agodi Prison Over Alleged N305 Million Scam

While welcoming the new Managing Director of Julius Berger Plc, the minister reiterated the need for construction companies working with the Federal Ministry of Works to prepare to make sacrifices in terms of value for money and realistic contract pricing, to encourage the much-needed road infrastructure revolution for the nation’s economic transformation, which is a cardinal agenda of the Renewed Hope administration of the President of the Federal Republic of Nigeria, His Excellency, President Bola Tinubu.

 

 

Channels TV



...To get more news updates, Join our WhatsApp Group (Click Here) and Telegram Group(Click Here)
Leave A Reply

Your email address will not be published.